[Construction Example] Multi-Drill Method (Equivalent to BG Method)
We will perform cutting, removal, and backfilling suitable for the site! A case of removing PHC piles that could not be completely taken out.
We would like to introduce a case study of underground obstacle removal conducted by our company. In Yokosuka City, Kanagawa Prefecture, we carried out the work using the multi-drilling method (equivalent to BG method). We removed PHC piles that could not be extracted using the pull-out method. Upon receiving notice that extraction was impossible, we promptly commenced work and successfully completed the project. 【Case Overview】 ■ Project Name: Multi-Drilling Method (Equivalent to BG Method) ■ Construction Date: May 12, 2022 ■ Location: Yokosuka City, Kanagawa Prefecture ■ Details: φ1000 GL-25m *For more details, please download the PDF from the related link or contact us.
- Company:東京テクノ
- Price:Other